Skip to main content
Question

help with a work ticket report

  • January 21, 2026
  • 3 replies
  • 47 views

Forum|alt.badge.img+3

I’m trying to run a report that shows me all the tickets scheduled for the next day, but I can only get it to show tickets whose Start Date is next day, not everything scheduled for tomorrow. 

I feel as though I have to be missing a simple filter setting or something - can anyone help? 

TIA!

3 replies

Kbaird
Forum|alt.badge.img+18
  • Brainy
  • January 22, 2026

Are you using anticipated or scheduled start date?


Forum|alt.badge.img+3
  • Author
  • New Participant
  • January 22, 2026

That’s the issue - is there a choice other that “start” date? If we’ve started the job previously, and are returning, is there a way to see that as well as the jobs that are actually starting that day?

 


Calvin-Aspire
Employee
Forum|alt.badge.img+16

If you go to the standard report there is the work ticket visit report, the scheduled date on that list is the date the visit is scheduled you can filter to tomorrow that should give you all the tickets that are scheduled for the next day.